MCD Announces $8.7 Million in Federal Funding for Three Dam Rehabilitation Projects
The Miami Conservancy District announced $8.685 million in federal funding to rehabilitate upstream concrete walls at Germantown, Englewood and Taylorsville dams, advancing needed improvements to the region’s century-old flood protection system.
Congressman Mike Turner, who helped secure the funding through the federal Community Project Funding process, joined MCD for the October 20, 2026 announcement. The funding is provided through the Federal Emergency Management Agency’s Pre-Disaster Mitigation program.
The three dams are part of MCD’s integrated system of five dry dams, upstream storage basins, levees, floodwalls and improved river channels. Together, these features reduce river flood risk for communities across southwest Ohio, protecting homes, businesses and infrastructure that support the regional economy.
![]()
Strengthening century-old structures
The rehabilitation will address deteriorated concrete and structural stability concerns in the upstream walls. Work will include replacing damaged concrete and adding drainage systems and rock anchors where needed to improve wall stability and long-term performance.
These walls withstand pressure from stored floodwater and water in the soil behind them. More than a century of exposure to weather, including repeated freezing and thawing, has also contributed to concrete deterioration. The improvements will use modern materials and engineering methods to strengthen the walls and reduce the risk of failure.
The combined preliminary construction estimate is approximately $13.1 million. The federal investment will cover about two-thirds of that estimate.
Germantown Dam
Germantown Dam has stored floodwater more than 594 times, reducing flooding downstream. Its upstream walls underwent repairs in 1970–71, and a high-water event in 2023 eroded portions of those earlier repairs. The preliminary construction estimate for the upstream wall project is approximately $3.86 million.
Englewood Dam
Englewood Dam has stored floodwater more than 748 times. Its upstream walls underwent repairs in 1970. The preliminary construction estimate for the upstream wall project is approximately $2.54 million.
Taylorsville Dam
Taylorsville Dam has stored floodwater more than 218 times. Its upstream walls underwent repairs in 1976. The preliminary construction estimate for the upstream wall project is approximately $6.72 million.
Continued investment in regional flood protection
The federal funding marks a substantial step in MCD’s broader effort to reinvest in the flood protection system. Inspections, monitoring and engineering analysis guide decisions about needed repairs and priorities across the dams, levees, floodwalls and other structures.
Reliable flood protection benefits the region beyond individual properties along the rivers. It helps protect transportation routes, utilities, employers and essential services that communities depend on every day.
Federal support reduces the amount of major rehabilitation costs that must be funded locally. Continued local investment remains necessary for daily operations, maintenance and additional capital improvements throughout the system.
For more than a century, the Miami Valley has benefited from the investment made by earlier generations. Today’s rehabilitation projects help preserve that protection for the generations ahead.
Learn more about MCD’s capital improvement projects.