News & Events more news

Posted: August 14, 2019

MCD accepting bids for Lockington Dam project

The Lockington Dam Right Wall Drain System and Concrete Repair project will include:

  • Partial concrete removal from the dam outlet works.
  • Excavating the dam embankment along the concrete wall and other areas.
  • Installing an aggregate filter drain with perforated and non-perforated pipe.
  • Hydrodemolition of existing concrete wall.
  • Forming and pouring the concrete wall top replacement.
  • Patching of concrete wall in limited areas.
  • Constructing a concrete apron along wall.
  • Constructing concrete revetment near outlets.
  • Installing a mechanically stabilized earth wall.
  • Installing drain pipe outlets including headwalls with check valves.

Sealed proposals will be received until 2 p.m. local time, Friday, September 6, 2019.

Visit MCD’s Plan Room, project No. 2019-021C, to access plans, specs, proposal forms, and addenda.